| Railway
Age Article  
Complete
Grade Separation at Birmingham, Ala.  [Note: this text has been reformatted to
single column layout for ease of reading on the screen.  Material on this
page transcribed from Railway Age article, August 19, 1933.]   Track
elevation permits conversion of the Louisville & Nashville station to the
two level type Marked improvements in the passenger
station facilities of the Louisville & Nashville at Birmingham, Ala.
comprised an important element of a $4,000,000 grade separation project recently
completed by that road through the business district of that city. The grade
separation was carried out jointly with the Southern, and with the Alabama Great
Southern, which occupies a location adjoining the right of way of the L & N
and crosses the tracks of the latter within the territory embraced in the
improvement. The project included the installation of an interlocking plant,
which controls the movements over the crossing, as well as through 26 switches
in the trackage adjacent to the crossing. In the Business Center of Birmingham The situation giving rise to a demand for
grade separation at Birmingham was typical of that encountered in cases where
the business center of a city has grown up adjacent to railway lines and where
comparatively level ground has favored the construction of grade crossings for
all intersection streets except those that were cut off at or near the railway
property lines to facilitate the development of adjacent land for freight and
passenger stations, team tracks and industries. The gradual increase in both
rail and street traffic eventually produced exceedingly objectionable
conditions. For example, at the passenger station, which fronts on Morris
Avenue, at the intersection with Twentieth street, serious interference with
station operation was imposed by grade crossings at Twentieth and Eighteenth
street, which passed directly over the two throats of the station layout. At the
same time, any plan for grade separation at once introduced the prospect of
decreased convenience in the arrangement of freight houses, team tracks and
industrial service requiring direct access to city streets at grade. Because of the physical conditions imposed
early efforts at grade separation had been confined to the construction of a
wooden viaduct to carry Twenty-second street over the tracks and driveways lying
between Morris and Powell avenues. About 1918 this overcrossing was supplemented
by another for Twenty-First street, but this was constructed of reinforced
concrete, and in anticipation of grade revision, was placed at a sufficient
elevation to permit a future raise of the track grades. A third viaduct, also of
reinforced concrete, was built for Twenty-Fourth street in 1924. Adopt Track Elevation Plan Thus, the construction of viaducts for the
three streets named above provided a satisfactory solution of the problem of
grade separation east of Twentieth street while avoiding any disturbance of the
existing relation of tracks to marginal streets, driveways, industrial plants,
etc. However, as indicated by the provision made for contemplated changes in
track grade, viaducts did not offer a satisfactory solution for grade separation
from Twentieth street west, and the plan agreed upon by the railways and the
city on October 31, 1928, called for track elevation, with underpasses for
Twentieth, Eighteenth, and Fourteenth streets, and the replacement of the wooden
viaduct at Twenty-Second street with a reinforced concrete structure. Among other advantages, this plan
permitted the development of a two-level plan for the passenger station, the
superiority of which was readily appreciated after long experience at Birmingham
with the shortcomings of a single-level layout for a through station. The
problem of serving industry tracks, team yards, etc. was met by the retention of
certain tracks on the street level between Fourteenth and Eighteenth streets,
where they are not crossed by an public thoroughfare. The adopted clear headroom of 14 ft. For
the underpasses plus the required floor thickness, developed a difference in
elevation of some 17 to 18 ft., of which from 3.5 to 5.5 ft. Was obtained by
depressing the streets and the remainder by elevation the tracks, the maximum
change of grade be9ing about 14 ft. With maximum run-off grades of 0.6 per cent,
the change of grade extended over a distance of 6,200 ft. on the Louisville
& Nashville and about 1,450 ft. farther at the west end on the Southern. The Layout of the Elevated Tracks (Click here to
open a map and profile of the overall project -- original is two pages wide) The elevated roadway was constructed to
accommodate from three to four Alabama Great Southern tracks and from three to
eight L & N tracks. As seen on the map, the project also involved the
raising of a rather complex track layout at the crossing, including the
construction of an incline for a Southern track connecting with tracks on the
surface in Powell avenue. In addition, the L. & N. Also had a small yard
between Fourteenth and Eighteenth streets, part of which was rebuilt on a 1.0
per cent grade descending eastward from the track elevation to the level of the
streets. This serves as a supporting yard for the team tracks and industry
service tracks between Fourteenth and Eighteenth streets. West of Fourteenth street there was
adequate right of way width to accommodated natural embankment slopes, but for
almost the entire distance from the east side of that street to a point about
150 ft. west of Twenty-Second street it was necessary to provide retaining walls
on both sides of the embankment. The walls built by the Alabama Great Southern
are mainly of the cantilever type, largely on pile foundations. The Louisville
& Nashville’s walls are largely of the counterfort type on spread
footings, but some 290 ft. of precast concrete crib wall was installed east of
Twentieth street, and east of that a wall of a cellular type was built on
account of the low bearing power of the supporting soil. The Underpasses While the project involves only three
underpasses, each of them is a large structure carrying 8 to 12 tracks and
spanning streets from 80 to 100 ft. wide. Four spans are provided in each
structure, with bents at the curb lines and the center of the street, and the
construction is reinforced concrete except for the use of encased steel beams
for track loading in the two roadway spans to obtain minimum floor depths for
these longer spans. In the longest spans, namely, 38 ft. for the Twentieth
Street underpass, 30-in., 200 lb. Carnegie beams were employed at a spacing of 1
ft. 6 ½ in. The sidewalk spans, and that portion of the roadway spans under the
platforms, consist of reinforced concrete beams and slabs. Design of Substructure The design of the substructure was
predicated on the requirements of the foundation, which is rock at widely
varying depths. In many locations this was not more than 10 ft. below street
level, but at other points it is 10 or more feet lower, with occasional
crevasses extending to far greater depths. The intermediate supports, at the
curb line and the center of the street, consist of bents made up of columns of
rectangular section connected at their tops by half-ellipse arches to forma
cross-girder or cap, these columns being extended to whatever depth was
necessary to reach rock. Attractive Portals The abutments are also composed of rows of
columns 3 ½ ft. by 1 ½ ft. in section (with the long dimension transverse to
the street), which function also as vertical beams to take the lateral earth
pressure of the embankments which is applied to a 10 in. curtain wall
constructed monolithic with the columns. This wall extends only a short distance
below the sidewalk level. The
underpasses are distinctive by reason of the exceptional attractiveness of the
portal design and the excellent workmanship obtained in the casting of the
moldings, panels and fine detailed ornamentation. Special care in the
construction of the forms and the use of 1 ~ 1 ½ ~ 3 mix for the fascia
concrete were responsible in part of the results obtained. The decks of these
structures were covered with asphalt and fabric waterproofing, protected with
asphalt plank. The lighting of these underpasses is out of the ordinary, special
pains having been taken to obtain an evenly distributed and diffused
illumination, but concealing the source from the eyes of vehicle drivers and
pedestrians. All lights are enclosed in weatherproof metal boxes with hinged
covers glazed with a diffusing glass, these boxes being set in recesses provided
for them in the concrete of such depth that the cover is blush with the concrete
surface. In the sidewalk spans these fixtures are installed overhead at a
spacing of about 19ft. while in the roadway spans they are placed at intervals
of 18 ft. in the filleted sides of the beams at the tops of the bents, as shown
in one of the illustrations. The Twenty-Second Street Viaduct The most recently constructed of the three
viaducts over the tracks, the one on Twenty-Second street, subsequent to its
replacement has a total length of 1,050-ft. including the approach embankments.
The structure proper has a length of 707.9 ft., center to center of end span
bearings and consists of 17 spans from 32 ft. to 56.5-ft. long, center to center
of piers. It is 70 ft. wide and accommodates a 56-ft. roadway and two 7-ft. wide
sidewalks. The structure consists of T-beam spans, composed of 14 lines of
girders and a slab floor4, supported on four-column bents and designed as
continuous spans between double-bent expansion joints at intervals of two to
four spans. There
are maximum ascending grades of 4 per cent and 3.71 per cent from the north and
south ends, respectively, to a summit on two spans over the north runoff from
the track elevation, the determining feature of the design being a span of 56 ½
ft. over the four southerly of these tracks. To reduce the depth of girders to a
minimum in this span, which is the middle span of a group of three between
expansion bents, joints were introduced 5 ft. 10 ½ in. From each end, so that
the middle 44 ft. 9 in. Could function as simple suspended span supported by
cantilever extensions from the bents. The tension reinforcement in the bottom of
the girders is continued across these joints but all other bars were
interrupted. However, the most novel feature of the construction is the detail
of the support for the suspended girders on the cantilever girders. This
consists of a structural steel bracket concreted into the cantilever beams, that
was formed, as shown in the sketch, to provide a sort of halved joint affording
two bearings for the suspended span girders as well as two horizontal bearing
areas for the distribution of the load on the cantilever girders. Improve Station Facilities Previous to the separation of grades, the
passenger station facilities of the L. & N. consisted of a station building
about 213 ft. by 49 ft. fronting on Morris avenue at Twentieth street,
supplemented by auxiliary buildings further west along Morris avenue and facing
on the south on a train shed of 90 ft. span and 510 feet length. This sheltered
five station tracks and the planked area between the tracks, and extended to the
station building. The elevated layout provides four
passenger train tracks with two island platforms, and two coach tracks with a
four-foot platform between them. These tracks are supported on an embankment
enclosed on the north side by a retaining wall with its exposed face 64.9 ft.
south of the old station. The transverse axis of the station track is at
Nineteenth street, and a subway leading to four passenger stairways to the
platforms was located there, while subways affording corresponding acce4ss to
baggage-truck elevator were located 335 ft. to the east and 339 ft. to the west. It was also necessary to amplify the
existing baggage and express facilities, and this was done by providing a space
for them 42 ft. 4 in. Wide by 440 ft. long, under the tracks from a point 18ft.
4 in. East of the passenger subway to a point 56 ft. 8 in. West of the west
baggage subway. This was made possible by setting back the retaining wall and
carrying the tracks on a reinforced concrete slab and column structure and
enclosing the face of this undertrack space with a concrete curtain wall set
flush with the remainder of the retaining wall. This space under the tracks is
used to house a baggage room, express room, and mail room, and provide
accommodations for station employees, coach maintenance forces , a room for
conductors, and station master’s office and transformer and switchboard rooms. (Click
here to view a floorplan of the station area.) A New Concourse The open area between the retaining wall
and the station buildings afforded ample room for the development of the
necessary concourse for intercommunication between the station and the
passenger-stairway subway and between the baggage, mail and express spaces and
the east baggage-elevator subway. To do this, a concrete wall enclosing large
areas of steel sash was constructed on top of the retaining wall, and steel roof
trusses of 50-ft. span were erected at 25-ft. centers to span between this wall
and the tops of the columns that formerly carried the north end of the old
trainshed roof. Purlins spanning between trusses support precast concrete roof
file. The station platforms are of concrete and
are covered with canopies having steel frames and cast-in-place concrete roof
slabs covered whit pitch and gravel roofing. The problem of support for the
canopy columns on filled ground was solved by setting them on concrete footings,
each of which rests on two creosoted piles. Another feature of the project was the
construction of a reinforced concrete warehouse with brick exterior walls, 80
ft. by 180 ft., which is located between Eighteenth and Seventeenth streets.
This building is two stories high, but the foundation and columns were designed
to permit its eventual construction to a height of six stories. Other new
facilities included a service building for mechanical department employees, a
brick telegraph office, a brick building housing soil-can cleaning facilities,
and a locomotive coaler and a cinder plant furnished by Fairbanks, Morse &
Co. The Interlocking The railway crossing west of Fourteenth
street is protected by an electric interlocking plant which was constructed
under contract by the Union Switch & Signal Company, Swissvale, Pa. As
seen on the map, the crossing embraces 13 individual track crossings, of which 6
have movable frogs. However, the plant also controls movements through 26
switches located within 850 ft. west and 1,150 ft. east of the tower, with the
result that the plant operates 6 movable frog crossings 26 switches, 26 derails
and 30 signals. The interlocking machine is a Union Type F, with 47 working
levers and 16 spare spaces. The signals are of the semaphore type, using Union
Style-T2 mechanisms and the switch machines are the Union Style-M2, operating on
110-volt direct current with Type-F circuit controllers mounted on separate
concrete foundations. The installation also includes a train annunciator system
providing push buttons on the station platforms for the use of conductors to
notify the towermen of the departure of trains so that he may clear the
requisite route. Not only was it necessary to rebuild and
rearrange all tracks serving the passenger train facilities, but it was also
required to abandon the old source of water supply and obtain water from the
local water company, construct a new high steel storage tank of 50,000 gal.
Capacity and provide a new distribution system, including 12-in. Water columns
as well as service boxes along the platforms. Corresponding provision was made
for steam service, vacuum cleaners and battery charging. In addition, the
telegraph, telephone and electric power lines, which had formerly been carried
on poles, were placed in underground conduits between Seventeenth and Twentieth
streets. A Complete Construction Program Because substantially all of the area
affected by the construction work is covered by tracks at a close spacing, it
was necessary to carry on the work in accordance with a carefully prepared
schedule that insured adequate provision for the handling of traffic at all
times, and because the tracks of the two roads are adjacent, it was necessary to
elevate their tracks concurrently. In general, the plan involved the
construction of the embankments and structures in long9tudinal strips, while
service was maintained on tracks continued in use on the surface until the
transfer could be made to tracks on the elevation. Also, because the city
insisted on a minimum of interference with pedestrian and vehicle traffic, it
was decided to complete the work on the Twenty-Second street viaduct first,
before blocking Fourteenth street, and complete the underpass at that street
before closing Eighteenth and Twentieth streets. Accordingly,
after completing the Twenty-Second street viaduct, the second stage of the
project was to build the retaining walls between Fourteenth and Eighteenth
streets, and raise the tracks across Fourteenth street under traffic to final
elevation, completing the run-off on the west end and introducing a temporary
run-off on the east at a 0.6 per cent grade which reached the original track
grade at Eighteenth street. Following this, falsework was driven at Fourteenth
street and the excavation made to permit the building of the underpass. The next step was to block Eighteenth and
Twentieth streets, handle L. & N. passenger trains to the east of the
station on a track north of the L. & N. freight station and to the west of
the station on a yard track that made a connection with the main line near
Fourteenth street. In addition, the L. & N. confined freight trains to its
northbound main track, while the A.G.S. diverted all train movements to its
southbound main track. These
two tracks were adjacent at about the middle of the proposed underpasses, and
the removal of all other tracks permitted work to proceed on the construction of
the two underpasses except for the space in the middle occupied by these two
operated tracks and a short section at the north end of the Eighteenth street
structure which had to be omitted to provide room for the temporary connection
to the L. & N. station from the west. While the work on the underpasses was in
progress, the retaining walls east of Twentieth street were constructed and the
grading was done on the approach fills to those parts of the underpass3es then
under construction. During this period, work proceeded also on those parts of
the L. & N. passenger subways that did not interfere with passenger service
under the trainshed. Transfer Traffic to High Level After this stage of the work was
completed, L. & N. and A.G.S. freight traffic was diverted to the high
level, thus permitting the middle section of the underpasses to be constructed.
While this was being done, the south butterfly shed and platform at the L. &
N. station were constructed, the adjacent fills made and the tracks laid, which
permitted the A.G.S. to complete its part of the work and provided the L. &
N. with two main tracks and three station tracks. The L. & N. then diverted
its passenger traffic to the high level which permitted the construction of the
north portal of the Eighteenth street underpass, the construction of the service
building under the station tracks and the retaining wall between Eighteenth an d
Twentieth streets. The remainder of the work was continued with no interference
with train movements. The improvement work at Birmingham was
designed and built under the direction of an engineering commission created by
the grade separation agreement and consisting of A. J. Hawkins, city engineer of
Birmingham; B. Herman, chief engineer of the Southern; and Edward Wise, Jr.,
special engineer of the Louisville & Nashville, representing W. H.
Courtenay, chief engineer. The cost of the grade separation work was divided
equally between the city and the railroads, each paying one half the cost of the
work on its property. Each railway designed and built its own retaining walls
and handled the grading on its own property with company forces but the plans
for the Twenty-Second street viaduct and the underpasses, as well as the station
facilities were prepared by the Louisville & Nashville, which also
supervised the construction under contract of these portions of the project. J.
W. Hoyt was resident engineer for the Louisville & Nashville. The contractors participating in the
project included Millsap & Parker, Birmingham, on the Twenty-Second street
viaduct; the Gould Construction Company, Nashville, Tenn., on the Fourteenth
street underpass; the Southern Construction Company, Birmingham, on the two
other underpasses and other station structures, such as the butterfly sheds,
concrete platforms and paving, and retaining walls; the Foster-Creighton
Company, Nashville, on the warehouse building and the service building under the
station tracks; A. J. Honeycutt, Birmingham on the passenger and baggage
subways; D. T. Underwood, Birmingham, on the concourse shed and several small
buildings; Walter T. Weaver, Birmingham, on the retaining walls between
Fourteenth and Eighteenth streets; the Otis Elevator Company, Atlanta, on the
elevators; the Union Signal Construction Company, Swissvale, Pa., on the
interlocking work, and various other contractors. About 50 separate contracts
were let during the course of the project. More on
L & N Station
 |